A 1. Leveling of the base layer: The cushion layer should be accurately level, and the height of the armor joint should be 10-40mm less than the thickness of the floor.
2. Positioning and laying out: Use a theodolite or laser level to determine the position, adjust the elevation by pulling a line, with an error of ≤ 2mm.
3. Cross connection fixation: Spring pins and easily breakable bolts are used for fixation. Four fixing points are required for cross connections, and three fixing points are required for T-shaped connections.
4. Concrete pouring: The vibration should be compacted to ensure that there are no honeycombs around the transfer plate, and poured until the edge is level.